Performance guidance
Document content and editorial review: approved on 2026-11-16 by Codex under the repository user’s delegated review. Approval covers this explanation and its stated evidence limits; semantic, mapping, lifecycle and target states remain independent.
Conceptual overview
%%{init: {'theme':'base','fontFamily':'Arial, sans-serif','themeVariables':{'lineColor':'#8792a2','textColor':'#f8fafc','nodeTextColor':'#f8fafc','primaryTextColor':'#f8fafc','arrowheadColor':'#8792a2','dropShadow':'none','useGradient':false,'edgeLabelBackground':'#252b36','fontFamily':'Arial, sans-serif','fontSize':'16px'}}}%%
flowchart TD
accTitle: From quality question to evidence
accDescr: Qualities inform a scoped scenario, which defines measures. Candidate techniques are compared with representative evidence before owner decisions.
Q["Quality Attribute: approved local meaning"]:::quality -->|frames| S["Scenario: workload and boundary"]:::context
S -->|defines| M["Measures: timing, work, resources"]:::measure
S -->|frames comparison of| T["Techniques: caching, scheduling, less work"]:::technique
M -->|inform| E["Representative evidence and uncertainty"]:::context
T -->|evaluate effects with| E
E -->|supports| D["Owner decision: pending"]:::context
classDef quality fill:#24452a,color:#f8fafc,stroke:#8792a2,stroke-width:2px
classDef context fill:#343c4b,color:#f8fafc,stroke:#8792a2,stroke-width:2px
classDef measure fill:#503824,color:#f8fafc,stroke:#8792a2,stroke-width:2px
classDef technique fill:#4b3049,color:#f8fafc,stroke:#8792a2,stroke-width:2pxText equivalent: Qualities frame a scenario, which identifies boundaries, workload and measures. Techniques need representative comparisons and correctness checks before an owner decision. The G01 example is hypothetical, with unapproved targets. This is an evaluation reading path, not an implemented service flow.
Provenance: the scenario method, measures and conditional techniques discussed below, with their recorded source limits. The arrows organize evaluation and owner review; they report no executed TDP test or approved target.
Sources and scope
This guidance is a proposal, not a TDP implementation observation or runtime verification. Tdp.Backend is the functional authority; no backend source was investigated for this hypothetical example. Consulted 2026-11-03:
- SEI, Deriving Architectural Tactics, Bachmann, Bass and Klein, CMU/SEI-2003-TR-004 (2003), sections 2.1 and 3: historical scenario and tactic method, not an ISO taxonomy.
- ISO/IEC 25010:2023 catalog, ISO, published edition 2: catalog evidence only. Full standard definitions and completeness were not accessible; secondary transcription supplies labels for review, not authoritative definitions.
- arc42 Q42 model, live page, no fixed edition stated: overlapping tags, not a tree. Its current contents may change.
The five linked concepts are separate approved local meanings; their applicability and mapping need owner review. No numerical commitment, priority or owner is approved.
Note: example, target and evidence are different. G01 supplies invented observations and illustrative criteria so readers can check the reasoning. Approving this explanation does not approve those criteria for TDP. An approved target would require a recorded owner decision for a named scenario; evidence from an executed test would require identifiable system/configuration inputs, workload, method, observations and verification limits. Even such a test would not automatically establish production behavior. No executed TDP test is reported here.
Timing and throughput
- Response time: elapsed time from a defined request boundary to its response, in milliseconds or seconds. State client/server boundaries and percentile.
- Latency: delay between specified events, in milliseconds or seconds; it may cover a network hop or part of a request rather than the whole response.
- Throughput: completed work per unit time, such as successful requests per second. State the success definition and observation window. Throughput alone conceals slow or failed requests.
These are measures, not separate quality attributes. Their usefulness depends on workload, data, boundary and error rate. See technical consequences.
Resources and channel capacity
CPU utilization is processor time consumed relative to stated available CPU over a window; memory utilization is bytes used or a stated fraction of a limit; and bandwidth utilization is transmitted bits per second or a fraction of a stated link rate. Record the denominator and aggregation. High utilization is not by itself proof of a bottleneck. Channel capacity is a communication limit under specified conditions, expressed for example in bits per second; it is not the same as observed application throughput. These are measures or limits, not independent quality concepts. Resource budgets need explicit owners and conditions.
Example: consumption is not automatically a failed budget. G01’s synthetic Run B reports a highest one-minute average CPU of 85% across two allocated cores. It fails because G01 explicitly requires each such average to stay below 80%. In a separate hypothetical scenario with no CPU acceptance limit, the same observation would support diagnosis, not a CPU-budget verdict. CPU limits are scenario-specific; the allocated cores and averaging window give the percentage its meaning. CPU use alone also does not prove that CPU caused the delay.
Aliases
The portable metadata records propose related mappings from Responsive and
Fast to time behaviour, limited respectively
to interactive response timing and a named task’s duration. They also propose
responsiveness as related to interactive time behaviour, and efficiency
as related to performance efficiency
only in its work-to-resource sense. The latter two labels come from the pinned
research intake, not freshly corroborated primary definitions. All four are
scoped hypotheses for review, not equivalence, approved applicability or
thresholds. Context and owner evidence may reject any proposed mapping.
Q42 dimensions
The Q42 page describes nine overlapping tags. Their practical prompts here are:
- Efficient: consider resources needed for useful work; a proposed related mapping to performance efficiency is recorded on that concept.
- Flexible: consider the cost of adapting a performance choice to change.
- Maintainable: consider whether tuning makes change and diagnosis harder.
- Operable: consider monitoring, configuration and incident response.
- Reliable: consider continued correct service under workload.
- Safe: consider consequences of timing failures in relevant contexts.
- Secure: consider security controls and their performance interactions.
- Suitable: consider whether the result meets the actual purpose.
- Usable: consider the effect of waiting and feedback on users.
These descriptions are crosswalk prompts, not definitions of other slices or assertions of ISO parentage. The scoped alias hypotheses above remain separate from Q42 classification.
Reusable scenario template
Copy this template for a specific quality decision. Fill every field, retaining proposal versus approval status and source limits. The six fields follow SEI CMU/SEI-2003-TR-004 section 2.1; the additional context prevents an isolated number from becoming an accidental requirement.
| Field | Fill in for the proposed scenario |
|---|---|
| Stimulus source | [Who or what generates the event?] |
| Stimulus | [What event occurs, including offered rate or change?] |
| Environment | [Workload, concurrency, dataset, cache state, faults and configuration] |
| Artifact | [System or component and exact measurement boundary] |
| Response | [Expected observable action, including error handling] |
| Response measure | [Threshold/distribution, units, observation window and success/error population] |
Record: [scenario identifier], [linked qualities], [stakeholder], [pending decision owner], [business value and rationale], [technical risk and evidence], [status: proposal/approved], [approval authority/date if approved], [verification method and representative environment], [uncertainty and next evidence]. A completed template describes a requirement or proposal; it does not report an observation.
G01 scenario
Illustrative only: a hypothetical TDP project-information read service, not the portal and not a claim about an existing endpoint. The six SEI fields are:
- Stimulus source: a simulated group of users.
- Stimulus: submit project-information read requests.
- Artifact: the hypothetical read service and its dependencies, measured from client request dispatch to complete response receipt.
- Environment: a representative test environment with up to 100 concurrent simulated users and 100,000 synthetic project records. Begin with an empty service cache, then ramp offered arrivals uniformly from zero to 50 requests/s over one minute and hold 50 requests/s for ten minutes. Record offered and actual arrivals, including requests rejected or delayed by the load generator.
- Response: return correct authorized information or a recorded error.
- Response measure: illustrative, unapproved: at least 95% of successful responses within 500 ms, achieved successful throughput of at least 49 requests/s and errors under 1% of arrived requests over the ten-minute hold. During that hold, one-minute average CPU across allocated cores stays below 80%, and peak total service memory stays below 2 GiB.
Record network rate and channel limit separately. The hold includes cache warming; separately record the cold-start ramp and repeat cold and warm runs rather than treating the hold as entirely cold. Record the distribution, errors, utilization and configuration, and compare results with a separately approved target. This is a documentation example; no test against TDP was executed or requested. Representative data, dependencies and load generation determine how far results can generalize.
Example: users and arrival rate describe different conditions. G01 offers 50 requests/s: 50 × 600 = 30,000 requests during the hold. Its limit of up to 100 concurrent simulated users is a separate condition, not 100 requests/s. A response measured at one request/s cannot establish the result at G01’s load. Check the actual arrivals as well: a generator that falls behind has not demonstrated the intended workload, even if the service reports short times.
What the scenario evaluates
A quality scenario evaluates whether a system satisfies an expectation under explicit conditions. A controlled baseline/treatment comparison evaluates the effectiveness of a technique, such as caching. The attribute supplies the question; it is not an independently measured intervention. The following examples teach both evaluations using G01’s workload. All observations and criteria below are synthetic and illustrative, not approved TDP requirements. Stakeholders and decision owners remain pending; no backend test was run.
Request journey and measurement boundaries
%%{init: {'theme':'base','fontFamily':'Arial, sans-serif','themeVariables':{'lineColor':'#8792a2','textColor':'#f8fafc','nodeTextColor':'#f8fafc','primaryTextColor':'#f8fafc','arrowheadColor':'#8792a2','dropShadow':'none','useGradient':false,'edgeLabelBackground':'#252b36','fontFamily':'Arial, sans-serif','fontSize':'16px','actorBkg':'#343c4b','actorBorder':'#8792a2','actorTextColor':'#f8fafc','actorLineColor':'#8792a2','signalColor':'#8792a2','signalTextColor':'#f8fafc','noteBkgColor':'#503824','noteTextColor':'#f8fafc','noteBorderColor':'#8792a2','labelBoxBkgColor':'#252b36','labelBoxBorderColor':'#8792a2','labelTextColor':'#f8fafc'},'look':'classic','sequence':{'useMaxWidth':false}}}%%
sequenceDiagram
accTitle: Hypothetical G01 read journey and timing intervals
accDescr: User wait includes client work before dispatch and after receipt. G01 measures dispatch to complete receipt. Server and dependency intervals cover smaller portions only.
participant U as User
participant C as Client
participant S as Read service
participant D as Data dependency
rect rgb(52,60,75)
U->>C: t0: request action
Note over C: Prepare request
C->>S: t1 dispatch, t2 service accepts
S->>D: t3: dependency call starts
D-->>S: t4: dependency completes
S-->>C: t5 service sends, t6 complete receipt
Note over C: Present result
C-->>U: t7: usable result
Note over U,C: Complete user wait: t0 to t7
Note over C,S: G01 response time: t1 to t6
Note over S,D: Service t2 to t5, dependency t3 to t4
endText equivalent: The user acts at t0. The client prepares and dispatches at t1; the service accepts at t2, calls a dependency at t3 and receives its result at t4. The service sends at t5; the client receives the complete response at t6 and presents a usable result at t7. Complete user wait is t0–t7; G01’s response time is t1–t6. Service t2–t5 and dependency t3–t4 are scoped intervals within that journey. They exclude other waiting.
Provenance: an authored hypothetical teaching flow for G01, not observed TDP architecture or evidence of an existing endpoint, client or datastore. Actors and the journey panel use Supporting context and notes use Measure or limit colors from the catalogue. The drawing omits retries, queues and cache branches; their delay still belongs in the measured response when present. It establishes no functional membership.
For one synthetic request, user wait is 480 ms, G01 response time is 400 ms, service time is 300 ms and dependency time is 180 ms. The dependency interval is included in service time; adding all four double-counts work. Measure each interval with a monotonic clock at its own boundary. Correlate spans with trace IDs; subtracting unrelated host timestamps requires clock-error accounting. Instrument complete user wait separately when that is the intended requirement.
Note: choose the interval before judging the result. In this synthetic request, the 180 ms dependency time is already inside the 300 ms service time, which is inside the 400 ms client response time. None replaces the 480 ms complete user wait. These are intervals for one request, not population percentiles; do not add them or treat one request as the G01 p95 result.
G01 worked results
Verification method (to apply, not executed): instrument dispatch and complete receipt at the load client, validate every response against the synthetic data and authorization oracle, and retain individual timings and outcomes. Treat timeouts, rejections, incorrect and unauthorized responses as errors, including apparently successful HTTP responses with wrong content. Use a 5 s timeout, report unfinished work separately and reconcile arrivals, completions and in-flight work at both edges of the hold. Record all one-minute CPU averages, total service CPU-seconds, peak memory and network rate. G01’s 600 s hold includes warming; repeat the cold ramp and warm runs separately with fixed configuration.
For the simplified arithmetic here, all 30,000 offered requests arrive in each hold, none are lost by the generator, and all finish within it; no work crosses its edges. CPU uses two allocated cores; memory covers the whole service, including its cache. The dependency’s resources are outside that accounting boundary and must be reported separately in a real comparison. Network peak is 12 Mbit/s on an illustrative 100 Mbit/s channel in both runs, with no proposed network acceptance threshold. These assumptions make the counters reconcilable; real boundary effects require the method above.
| Observation over the 600 s hold | Run A | Run B |
|---|---|---|
| Arrivals at 50 requests/s | 30,000 | 30,000 |
| Correct, authorized successes | 29,850 | 29,400 |
| Errors (including timeouts/incorrect results) | 150 | 600 |
| Successful throughput: successes / 600 s | 49.75 requests/s | 49.00 requests/s |
| Error fraction: errors / arrivals | 0.50% | 2.00% |
| Successful-response p95 | 420 ms | 680 ms |
| Highest one-minute average CPU / two allocated cores | 65% | 85% |
| Peak total service memory | 1.2 GiB | 1.4 GiB |
| Joint illustrative G01 result | Satisfied | Failed: timing, errors and CPU |
Run B meets the throughput threshold of at least 49 requests/s but fails G01. Its errors exceed the strict under-1% criterion, its p95 exceeds 500 ms and CPU exceeds the strict below-80% criterion. Faster counters cannot compensate for those failures. Run A satisfies all the illustrative criteria for this window; it establishes neither a production guarantee nor an approved TDP target.
Example: reconcile outcomes before accepting throughput. Run B has 29,400 correct authorized successes + 600 errors = 30,000 arrivals. Its 29,400 / 600 = 49 successful requests/s meets only the throughput criterion; 600 / 30,000 = 2% errors fails the separate error criterion. An HTTP success with incorrect or unauthorized content belongs in errors, not in useful work. The other failed criteria still apply; satisfying one measure cannot offset another failure.
Interpretation and decision: retain Run A as a candidate for repeated, representative evaluation; investigate Run B’s tail delay, errors and CPU pressure before proposing acceptance. Business value is reduced waiting for the selected read journey; technical risk includes unrepresentative data, cache reuse and dependency behavior. Applicability, target approval and the responsible owner remain pending. A real decision needs repeated runs and recorded uncertainty.
Percentiles and populations
Sort the 29,850 successful response times in Run A. Use the nearest-rank convention: p95 is value at rank ceil(0.95 × 29,850) = 28,358, counting from one. This synthetic distribution makes the calculation reproducible:
| Response time for every member of the bucket | Successful responses | Cumulative count |
|---|---|---|
| 300 ms | 27,000 | 27,000 |
| 420 ms | 1,400 | 28,400 |
| 500 ms | 1,000 | 29,400 |
| 900 ms | 450 | 29,850 |
Rank 28,358 falls in the 420 ms bucket, so p95 = 420 ms. Exactly 29,400 / 29,850 = 98.49% of successes finish within 500 ms, satisfying at least 95%. There are still 450 successes taking 900 ms. p95 describes a population cutoff, not the worst request or a promise that every user waits 420 ms. The 150 errors are outside this percentile population and remain in the error calculation. Dropping them from both reports would hide failure. Do not average per-minute p95s to obtain the hold p95; aggregate the underlying observations or a suitable distribution representation with its approximation error stated.
Note: read p95 as a cutoff, not a promise to each user. The rank selects one value in the sorted success population. Here 28,400 of 29,850 successes are at or below 420 ms, so at least 95% meet that cutoff even though some take 900 ms. The 150 errors have not disappeared: they remain in the separate arrivals-based error fraction. A low success-only p95 could coexist with many errors, which is why the joint result needs both reports.
G01-C capacity variant
This variant keeps G01’s service, dataset and timing boundary and varies demand. It evaluates capacity; it does not implement scaling.
| Scenario component | G01-C, illustrative proposal |
|---|---|
| Stimulus source | Simulated users driven by the same load client as G01. |
| Stimulus | Offer 40, 50 and 60 requests/s in separate runs. |
| Environment | G01’s 100,000 synthetic records, two service cores and up to 100 concurrent users; fixed configuration. Reset cache before each one-minute uniform ramp to the selected rate, then hold for 600 s, including warming. |
| Artifact | The hypothetical read service and dependencies, client dispatch to complete receipt. |
| Response | Return correct authorized information or a recorded error; expose saturation and generator shortfalls. |
| Response measure | At each rate: successful-response p95 ≤ 500 ms, errors < 1% of arrivals, successful throughput ≥ 98% of offered rate, each one-minute CPU average < 80%, peak service memory < 2 GiB. |
The relative throughput criterion is a variant-specific illustrative rule: at 50 requests/s it equals G01’s 49 requests/s. It avoids imposing G01’s fixed 49 on a 40 requests/s experiment. Timing, error and resource constraints are retained.
Method and population: repeat G01’s instrumentation and correctness oracle at each load, retaining cold ramps and hold populations separately. Here offered and arrived counts match, no work crosses hold edges, and each row is a synthetic 600 s hold. CPU reports the highest one-minute average across the two allocated cores. Generator delays or rejections would invalidate an unqualified claim about the offered rate; record them alongside service results.
| Offered requests/s | Arrivals | Successes / errors | Successful requests/s | Error fraction | Successful p95 | CPU | Peak memory | Joint result |
|---|---|---|---|---|---|---|---|---|
| 40 | 24,000 | 23,880 / 120 | 39.80 | 0.50% | 360 ms | 52% | 1.1 GiB | Satisfied |
| 50 | 30,000 | 29,850 / 150 | 49.75 | 0.50% | 420 ms | 65% | 1.2 GiB | Satisfied |
| 60 | 36,000 | 35,100 / 900 | 58.50 | 2.50% | 760 ms | 88% | 1.5 GiB | Failed |
Interpretation and decision: 50 requests/s is the highest tested passing load, while the tested 60 requests/s fails timing, error, throughput (minimum 58.8 requests/s) and CPU criteria. Achieved throughput rose from 49.75 to 58.50 while service quality deteriorated. These coarse steps bracket a candidate boundary; they do not prove the exact maximum, long-term sustainability or a safe production operating point. Refine steps between 50 and 60, repeat runs and include fault/dependency variation before choosing headroom. Business value is demand planning; technical risk is a limit hidden by short or unrepresentative runs. The owner, acceptable headroom and any approved limit remain pending.
Note: the highest tested pass is not the exact capacity. The synthetic sweep tests three rates. It does not test every rate between 50 and 60 requests/s, nor show how long a passing result persists. A chosen operating limit would also need an owner decision about uncertainty and headroom, rather than simply adopting the highest passing row.
G01-E efficiency variant
This controlled comparison evaluates a caching technique through performance efficiency and resource utilization, retaining G01’s timing and correctness constraints.
| Scenario component | G01-E, illustrative proposal |
|---|---|
| Stimulus source | The same simulated users and a controlled synthetic update driver. |
| Stimulus | Replay identical 50 requests/s read traces and ten recorded updates during each 600 s hold. |
| Environment | G01’s dataset, up-to-100 concurrency, two allocated cores, one-minute ramp and ten-minute hold. Hold begins after an empty-cache ramp; warming remains included. Fix read-key popularity, update times, payloads, dependency version, authorization controls and instrumentation across variants. |
| Artifact | Hypothetical read service, including cache; total CPU-seconds across its two cores and peak service memory. Record dependency cost separately. |
| Response | Return correct authorized results. In this example, reads dispatched after an acknowledged update must see that update or a newer version; compare with an oracle. |
| Response measure | Retain all G01 criteria. Additionally, treatment CPU-seconds per correct read must be at least 20% lower than baseline, memory < 2 GiB, and zero stale or unauthorized responses in the checked population. All criteria are illustrative and unapproved. |
Verification method: replay the same seeded read/update trace with caching disabled, with invalidation-aware caching, and with TTL-only caching. Reset data and cache before each ramp; keep hardware, configuration and measurement overhead equivalent. Alternate run order and repeat trials to separate effects from drift. Record hits, misses, evictions, invalidation delay and update/read ordering; compare versions after acknowledged updates and exercise permission changes. The synthetic rows below are individual equivalent 600 s holds, not statistical evidence. Error and throughput accounting follows G01 with no edge work.
| Observation | Baseline: no cache | Treatment: invalidation-aware cache | Rejected alternative: TTL only |
|---|---|---|---|
| Arrivals | 30,000 | 30,000 | 30,000 |
| Correct successes / errors | 29,850 / 150 | 29,850 / 150 | 29,730 / 270 |
| Successful requests/s | 49.75 | 49.75 | 49.55 |
| Error fraction | 0.50% | 0.50% | 0.90% |
| Successful-response p95 | 480 ms | 420 ms | 400 ms |
| Total service CPU time | 1,080 CPU-s | 648 CPU-s | 600 CPU-s |
| Highest one-minute CPU average / two cores | 95% | 65% | 60% |
| Peak service memory | 0.8 GiB | 1.2 GiB | 1.2 GiB |
| Stale / unauthorized responses included in errors | 0 / 0 | 0 / 0 | 120 / 0 |
| CPU-s / correct read | 0.03618 | 0.02171 | 0.02018 |
| Joint illustrative result | Fails G01 CPU constraint | Satisfies G01 and comparison criteria | Fails zero-stale criterion |
The baseline uses 1,080 / (600 × 2) = 90% average CPU over the hold, which can coexist with a 95% highest one-minute average. Treatment uses 54% over the hold, with a 65% highest minute. Correct reads per CPU-second rise from 29,850 / 1,080 = 27.6 to 29,850 / 648 = 46.1. CPU cost per correct read falls by 1 − (648 / 29,850) / (1,080 / 29,850) = 40%, exceeding the illustrative 20% reduction. Peak memory rises by 0.4 GiB, or 50%, so this is a trade-off rather than an unconditional improvement in every resource.
Note: a ratio answers a different question from a budget. In this synthetic comparison, 648 CPU-seconds / 29,850 correct reads is about 0.02171 CPU-seconds per correct read. That ratio describes resource cost per useful result; G01’s CPU percentage limit constrains utilization over time. Both can matter, but a better ratio does not waive timing, correctness or memory criteria.
TTL-only results look faster and consume less CPU, but 120 stale responses fail the explicit correctness criterion even though total errors remain below 1%. They are excluded from useful work and included in errors. A hit-rate or timing improvement cannot authorize weaker correctness. Invalidation-aware caching is a candidate for further verification, not a technique proven effective in TDP.
Interpretation and decision: the synthetic treatment meets the comparison criterion under the chosen conditions, while the baseline fails CPU and TTL-only fails correctness. Evaluate whether reduced compute work justifies extra memory, invalidation engineering and operational cost. Business value is preserving timely reads at lower compute cost; technical risk includes missed invalidations, authorization-key errors and poor cache reuse. Target approval, acceptable freshness semantics, cost preference and the decision owner remain pending.
Caching alternatives and verification
These alternatives apply only when the G01 data and authorization semantics permit reuse. They describe proposed techniques, not an existing TDP design.
| Alternative | Expected benefit and memory cost | Invalidation and correctness | Limits, cost and verification |
|---|---|---|---|
| No cache | Simple reference behavior; no retained response cache. Repeated reads consume dependency work. | Read through to the authoritative dependency; still verify its consistency and authorization behavior. | Establish the baseline’s timing, CPU and dependency cost. Verify all G01 constraints; simplicity does not ensure adequate capacity. |
| Bounded per-service cache with TTL | Reuse repeated reads; allocate a bounded memory budget plus key/metadata overhead. | TTL limits retention but permits stale reads before expiry. Include authorization scope and representation in keys; test permission changes. | Low hit rates, cold starts, evictions and duplicate fills may erase benefit. Test expiry, updates, restarts and skewed keys; TTL alone fails G01-E’s post-update rule. |
| Bounded per-service cache with update invalidation | Reuse reads while removing or replacing entries when acknowledged updates occur; consumes cache memory and invalidation metadata. | Coordinate update acknowledgments and cache state across instances, and handle lost events and races. Invalidation alone does not prove freshness. | More implementation, telemetry and recovery effort. Test delayed/lost invalidations, concurrent updates and permissions; measure end-to-end correctness and memory peaks. |
Choose by the scenario’s correctness rule, reuse distribution and full cost boundary. Per-instance duplication can increase total memory; a shared cache would introduce another dependency and needs a separately scoped evaluation. Scheduling and reducing work remain conditional alternatives in the design checklist; this pilot implements none of them.
Lifecycle
Runtime refers to behavior and resource use while the system runs; development-time refers to evaluation and feedback while designing or changing it. Each quality has its own proposed assessment and rationale. Both may apply; empty assessed and unassessed have different meanings. These are reading aids, not inherited membership or a framework classification.
Example: the test date does not change what is measured. A developer could run G01 before release and measure the service’s response times under load. The same kind of service observation could inform runtime monitoring. Neither measures how quickly the developer works or how long the build takes. This explains the proposed reading dimensions; it does not confirm their assignments.
Prioritization
For each proposed scenario record its stakeholder and decision owner (pending), business value (low, medium or high with rationale), technical risk (low, medium or high with evidence), uncertainty and next evidence needed. Compare options and costs qualitatively with the owner; record the decision and date when made. No formula, ranking, budget or priority is approved by this pilot.
Design checklist
- Identify the user journey, artifact, boundary and workload, including data and cache state. Select the relevant linked qualities and verify applicability.
- Specify source, stimulus, environment, response and measurable outcome; state units, windows, error criteria and whether targets are proposed or approved.
- Consider reducing work, caching and scheduling only when prerequisites hold; record build and operating costs, failure modes, correctness and interactions.
- Choose representative measurement and comparison methods, capture uncertainty, assign a decision owner and revisit after changes. A measurement or source reference alone is not evidence of production behavior.